CalculationTime

Home, Trade & Construction

Excavation Calculator

Estimate excavation volume from length, width and depth, with cubic yards, cubic metres, loose spoil, truckload checks, cost estimate and a printable dig or quote note.

Default example25 yd³ loose spoil30 ft × 12 ft × 18 in ÷ 12 = 1.5 ft × 1 section(s) = 540 ft³ bank volume = 20 yd³ / 15.2911 m³ · with 25% swell = 25 yd³ / 19.1139 m³ loose spoil · about 3 load(s) at 10 yd³/load · rough estimate 875.00 at 35.00/yd³

Calculator

Working calculator

Live result25 yd³ loose spoil30 ft × 12 ft × 18 in ÷ 12 = 1.5 ft × 1 section(s) = 540 ft³ bank volume = 20 yd³ / 15.2911 m³ · with 25% swell = 25 yd³ / 19.1139 m³ loose spoil · about 3 load(s) at 10 yd³/load · rough estimate 875.00 at 35.00/yd³
Formula used

Depth feet = excavation depth inches ÷ 12. Bank cubic feet = length feet × width feet × depth feet × number of sections. Bank cubic yards = bank cubic feet ÷ 27. Bank cubic metres = bank cubic yards × 0.764554857984. Loose spoil cubic yards = bank cubic yards × (1 + swell percent ÷ 100). Truckloads = ceiling(loose spoil cubic yards ÷ truck capacity cubic yards). Cost estimate = loose spoil cubic yards × rate per cubic yard.

This is the method behind the answer, so the result can be checked rather than simply trusted.

Visual grid

This result measures part of the space you live in

Length, area, volume and material estimates are grid problems too: measure the space, account for edges and allowances, then turn the pattern into a number you can use.

Micro-timehours, minutes, shiftsHuman scaledays, weeks, projectsMacro-timemonths, years, calendars
Measured output25 yd³ loose spoil

Space calculations turn a real surface, room, run or volume into cells, edges and allowances that can be quoted, ordered or checked.

CalculationTime

Excavation Calculation Report

Report date:

25 yd³ loose spoil30 ft × 12 ft × 18 in ÷ 12 = 1.5 ft × 1 section(s) = 540 ft³ bank volume = 20 yd³ / 15.2911 m³ · with 25% swell = 25 yd³ / 19.1139 m³ loose spoil · about 3 load(s) at 10 yd³/load · rough estimate 875.00 at 35.00/yd³

Inputs

Excavation length
30 ft
Excavation width
12 ft
Excavation depth
18 in
Matching sections
1
Loose spoil swell
25 %
Truck capacity
10 yd³/load
Excavation or disposal rate
35 $/yd³

Method

Depth feet = excavation depth inches ÷ 12. Bank cubic feet = length feet × width feet × depth feet × number of sections. Bank cubic yards = bank cubic feet ÷ 27. Bank cubic metres = bank cubic yards × 0.764554857984. Loose spoil cubic yards = bank cubic yards × (1 + swell percent ÷ 100). Truckloads = ceiling(loose spoil cubic yards ÷ truck capacity cubic yards). Cost estimate = loose spoil cubic yards × rate per cubic yard.

  1. For one 30 ft by 12 ft excavation at 18 inches average depth, depth = 18 ÷ 12 = 1.5 ft. Bank volume = 30 × 12 × 1.5 = 540 ft³, or 20 yd³. With 25% swell, loose spoil is 25 yd³, about 3 truckloads at 10 yd³ per load.

Assumptions

  • The calculator treats each section as a rectangular excavation with an average depth entered by the user.
  • Depth is entered in inches and converted to feet before volume is calculated.
  • Loose spoil swell is shown separately because excavated soil, clay, gravel and mixed fill can occupy more space after digging than it did in the ground.
  • Truckload and cost outputs are planning checks only; real loading, road limits, skip sizes, access, dumping rules and minimum charges can change the job.

Notes

Use this space on the printed report for client, supplier, classroom, job-location, measurement, quote or approval notes.

Source: https://calculationtime.com/calculators/excavation-calculator

This report shows the calculation inputs, formula, assumptions and result for review. It is not legal, payroll, tax, engineering, financial or academic advice unless a qualified professional confirms the applicable rules.

Formula

Depth feet = excavation depth inches ÷ 12. Bank cubic feet = length feet × width feet × depth feet × number of sections. Bank cubic yards = bank cubic feet ÷ 27. Bank cubic metres = bank cubic yards × 0.764554857984. Loose spoil cubic yards = bank cubic yards × (1 + swell percent ÷ 100). Truckloads = ceiling(loose spoil cubic yards ÷ truck capacity cubic yards). Cost estimate = loose spoil cubic yards × rate per cubic yard.

Worked example

For one 30 ft by 12 ft excavation at 18 inches average depth, depth = 18 ÷ 12 = 1.5 ft. Bank volume = 30 × 12 × 1.5 = 540 ft³, or 20 yd³. With 25% swell, loose spoil is 25 yd³, about 3 truckloads at 10 yd³ per load.

Professional note

Master’s Tip: print both bank volume and loose spoil volume. The measured hole and the material hauled away are not the same thing, and mixing those two numbers is a common reason excavation quotes miss truck space or disposal cost.

Regional and unit assumptions

Standard or basis: rectangular volume arithmetic with 27 cubic feet per cubic yard and 1 cubic yard ≈ 0.764554857984 cubic metres. Soil swell is job-specific; confirm the swell factor, truck capacity, disposal rules, utility locating, shoring and safety requirements with the contractor or local authority.

Assumptions and limitations

Methodology & Accuracy

How this calculator is checked

CalculationTime pages are built around visible arithmetic: the formula, assumptions, worked example and practical limitations are shown so the result can be checked rather than simply trusted.

Formula used

Depth feet = excavation depth inches ÷ 12. Bank cubic feet = length feet × width feet × depth feet × number of sections. Bank cubic yards = bank cubic feet ÷ 27. Bank cubic metres = bank cubic yards × 0.764554857984. Loose spoil cubic yards = bank cubic yards × (1 + swell percent ÷ 100). Truckloads = ceiling(loose spoil cubic yards ÷ truck capacity cubic yards). Cost estimate = loose spoil cubic yards × rate per cubic yard.

Standard or basis

Standard or basis: rectangular volume arithmetic with 27 cubic feet per cubic yard and 1 cubic yard ≈ 0.764554857984 cubic metres. Soil swell is job-specific; confirm the swell factor, truck capacity, disposal rules, utility locating, shoring and safety requirements with the contractor or local authority.

Where a calculator follows a named legal, trade or industry standard, that standard is cited visibly. Otherwise the page uses transparent general arithmetic and states its limits.

Master's Tip

Master’s Tip: print both bank volume and loose spoil volume. The measured hole and the material hauled away are not the same thing, and mixing those two numbers is a common reason excavation quotes miss truck space or disposal cost.

Related calculators

Questions

How do I calculate excavation volume?

Multiply excavation length by width by average depth. Convert depth to feet first if it is measured in inches, then divide cubic feet by 27 to get cubic yards.

What is bank volume in excavation?

Bank volume is the volume of material in the ground before it is dug. Loose spoil volume is usually larger because soil expands when excavated and disturbed.

Why does the calculator include swell percent?

Swell percent estimates how much extra space loose excavated material may occupy. It helps compare the measured hole with truck, skip or disposal capacity.

Can this estimate trench or footing excavation?

Yes for a simple rectangular trench, pit or pad if you enter the length, width and average depth. Irregular shapes should be split into sections and checked separately.

What should I print for an excavation quote?

Print the length, width, average depth, number of sections, bank cubic yards, loose spoil allowance, truckload check, rate, formula, date, page URL and site notes.

Calculation note

Excavation estimating uses simple volume math, but the useful job record separates the measured in-ground cut from loose material that must be moved, loaded and disposed of. That distinction keeps the calculation practical instead of just geometric.

The hole is measured before the truck is ordered

Length, width and average depth describe the bank volume of the planned cut. That is the geometric starting point for the excavation record.

Loose soil changes the hauling question

Once material is dug, it is no longer packed in place. Showing swell separately helps a homeowner or contractor compare the planned cut with truck, skip and disposal capacity.

A printed excavation note keeps safety outside the arithmetic

The printout is useful for quantities and quote conversations, but it does not replace utility locating, shoring, access planning, drainage design or local permit checks.